tfs2012 - TFS 2012 Burndown Chart Not Updating -



tfs2012 - TFS 2012 Burndown Chart Not Updating -

i've got problems tfs burndown chart. i've created iteration (sprint) no start - end date. added working items - tasks each corresponding start - end date (lets 10/06/2014). 6 days have passed since realized whole iteration (sprint) did not have start - ending dates (10/06/2014 - 27/06/2014), i've added those, now... burndown chart showing progress dates 16/06/2014 current date, finish date: 27/06/2014

most of working items (tasks) within iteration - sprint have start, in progress , finished within current dates: 10/06/2014 - 16/06/2014.

please advice.

not sure how tasks have starting/ending dates. thought default templates had work remaining on tasks. anyways, burndown operates off work remaining fields of tasks, need update appropriately.

tfs tfs2012